Project Update as of June 15, 2009

 

The cannons have arrived at Texas A & M. A public hearing on Cannon Square has been scheduled for Saturday, July 18th at 9 a.m. at Borough Hall. Also, currently it is anticipated that artist's renderings may be viewed at Borough Hall after July 6th.



Project Update as of June 3, 2009

 

The cannons are en route to Texas A & M.



Project Update as of May 18, 2009

 

The following motion carried: "That the overall elevation of Cannon Square will not change with the exception of minor modifications necessary for beautification." Another public meeting will be scheduled when supporting documents and visuals are ready from the landscape architect.



Project Update as of April 8, 2009

 

The landscaping plan is still under review and will be presented to Borough residents sometime later this year. All parts of the cannons are now in storage in Pawcatuck. Plans are now in progress for shipping the cannon tubes to Texas for restoration. The Borough has applied to the State of Connecticut for reimbursement of $20,000 for the project, and should receive the funds shortly.



Project Update as of March 19, 2009

 

After hearing new input regarding the landscaping plan for Cannon Square, the Board of Warden and Burgesses have requested that architect Peter Cummin of Cummin Associates review the current plan in light of the new input.  This review process has caused a change in the project schedule.  

 

As of now, the cannons are being restored at three different locations:  wheels in PA, carriages in Pawcatuck, and tubes at a special facility in Texas.  The total project budget is now estimated at $95,000, with almost 75% being used for the cannons themselves.  Landscaping will begin in the spring of 2010 with a target completion date of Memorial Day 2010.  

 

To date, 28 citizens of our community have donated $54,000 for this project, the Borough is providing $10,000 and the State of CT has approved $20,000 for the project.

 

Project Update as of December 19, 2008

 

At their meeting on December 15, the Board of Warden & Burgesses voted 6 to 1 to proceed with the Cummin Plan for Cannon Square with an ongoing review of the tree selection. Just before that meeting, an anonymous donor contributed $30,000 to the project and requested that it be used for the electrolytic bath process to permanently preserve the two cannon tubes.  This process will begin in 2009 and will be completed in 2011, with one tube being off-site at a time.  

 

All other cannon restoration and landscaping will be finished by June of 2009...just in time for a special 4th of July celebration at Cannon Square.

 

Project Update as of December 4, 2008

 

On December 4, the Borough of Stonington mailed over 500 letters to all of the taxpayers in the 06378 zip code.  The letter outlined much of the information shown below and invited all citizens to a special public meeting to be held

 

Project Update as of December 2, 2008

 

The Borough of Stonington owns this historic property and is overseeing the entire project.  The SVIA is assisting in fundraising and project management.  The Stonington Historical Society has been involved from the beginning, researching the history of this special place.

 

Our project consists of two categories of work:

 

The Cannons  Restoration of the cannon tubes, wheels and carriages will take place in the Amish country of Pennsylvania and in Pawcatuck, CT.

The Grounds  This work includes trees, handicap access, flagpole, topsoil, grass, cannon mounts, etc.

 

The two cannons will be restored off-site this winter and, while they are away, the work on the grounds will begin.  Soon, you will see a temporary sign advising the public why the cannons are missing and what is happening to the square.  The cannons will be returned in June of 2009, and landscaping will be completed after the restored cannons are in place.

 

 Financial Details:

 

http://waterstreetweb.com/Symb075c00b700f000000000.pngTotal project budget is $68,000 with 2/3 of the expense related to the cannons.

http://waterstreetweb.com/Symb075c00b700f000000000.pngThe Borough stake in this entire project is $10,000 (not $99,150 as implied in the recent petition).  

http://waterstreetweb.com/Symb075c00b700f000000000.pngA combination of state and private funding will cover the remaining $58,000.

 

On Tuesday morning, Dec. 2, Warden Don Maranell oversaw the placement of the temporary sign at Cannon Square.

 

Since October 20, when the Warden & Burgesses approved the project, a group of Borough citizens attended the next board meeting and challenged certain aspects of the project.  After hearing their input, the board has taken steps to better understand the total scope of the project and to explore ways that the plan could be modified to best serve the interests of all Borough citizens; past, present and future.  

 

Part of the problem to date has been the lack of factual information about the project, including the rationale behind the landscaping plan developed by Cummin Associates.  The Warden & Burgesses are sending out a letter this week explaining the facts about the project and inviting everyone to a meeting at Borough Hall on Saturday, December 13, at 2 PM.  Following that meeting, the board will finalize their plans for the Cannon Square Restoration Project.

 

Project Update as of October 20, 2008

 

On the evening of October 20, The Board of Warden and Burgesses unanimously approved the Cannon Square restoration project. The cannons will be removed in November and a temporary sign will be at the site during their absence.

 

Project Update as of August 18, 2008

 

A public review meeting was held at Borough Hall on August 16 at 10 AM.  The meeting was chaired by Warden Don Maranell and featured presentations by:

 

http://waterstreetweb.com/Symb075c00b700f000000000.pngJim Hicks, SVIA President and Project Coordinator

http://waterstreetweb.com/Symb075c00b700f000000000.pngSarah Blair, Borough Burgess and Commissioner of Parks and Trees

http://waterstreetweb.com/Symb075c00b700f000000000.pngBob Abramson, Cannon Restoration Engineer

http://waterstreetweb.com/Symb075c00b700f000000000.pngJim Boylan, Historian (representing Stonington Historical Society.

 

For the most part, our plan was received very well and there appears to be a growing enthusiasm in the Borough.  The current budget stands at $70,000 with about 60% of that devoted to the cannons themselves.  The remaining funds will be used to ensure that the finished product will convey the beauty, dignity and care that this place of honor deserves.

 

Project Update as of July 30, 2008

 

http://waterstreetweb.com/Symb075c00b700f000000000.pngArchitect Peter Cummin proposes a landscape plan to beautify the site in keeping with historical precedent; his plan includes the planting of (high canopy) Princeton Hybrid Elms at each of the four corners.

http://waterstreetweb.com/Symb075c00b700f000000000.pngKen Geer has prepared an estimate for the earth, stone and lawn work required to execute the plan.  $25,000

http://waterstreetweb.com/Symb075c00b700f000000000.pngOur latest estimate from Bob Abramson for the cannons is $31,200; this does not include the costly and time-consuming electrolytic reduction process that we may defer for a later project.

http://waterstreetweb.com/Symb075c00b700f000000000.pngOther budget items include:  irrigation system, temporary and permanent signage, additional trees and planting costs, and transportation costs.

http://waterstreetweb.com/Symb075c00b700f000000000.pngTotal Budget is now estimated at $70,000.

Project Sequence (Approval and Planning in 2008; execution in 2009)

http://waterstreetweb.com/1x1.gif

http://waterstreetweb.com/Symb075c00b700f000000000.pngGet price quotes; prepare budget and project plan schedule. July of 2008.

http://waterstreetweb.com/Symb075c00b700f000000000.pngPrepare a rendering of the finished project.  Peter Cummin should complete by Aug 15.

http://waterstreetweb.com/Symb075c00b700f000000000.pngPresent budget and plan to Borough officials. July 2008

http://waterstreetweb.com/Symb075c00b700f000000000.pngHold public meeting in August of 2008.

http://waterstreetweb.com/Symb075c00b700f000000000.pngGain approval from the Board of Warden and Burgesses by September 1.

http://waterstreetweb.com/Symb075c00b700f000000000.pngBegin fundraising process: businesses, nearby residents, SHS...

http://waterstreetweb.com/Symb075c00b700f000000000.pngPrepare signs for the square to "tell our story" while the cannons are missing. Oct. of 2008

http://waterstreetweb.com/Symb075c00b700f000000000.pngRemove the fence and dispose.  January of 2009.

http://waterstreetweb.com/Symb075c00b700f000000000.pngRemove cannons for restoration. (will be gone for an estimated 10 weeks)

http://waterstreetweb.com/Symb075c00b700f000800000.pngRemove concrete cannon mounts.

http://waterstreetweb.com/Symb075c00b700f000800000.pngTemporarily remove two remaining trees.

http://waterstreetweb.com/Symb075c00b700f000800000.pngRemove earth to a level 6 inches below the curb height...

http://waterstreetweb.com/Symb075c00b700f000800000.pngPlace concrete mounting slabs for cannons (to be buried...per Bob Abramson and Peter Cummin)

http://waterstreetweb.com/Symb075c00b700f000800000.pngFill earth back up to curb height with good topsoil.

http://waterstreetweb.com/Symb075c00b700f000800000.pngInstall underground irrigation system.

http://waterstreetweb.com/Symb075c00b700f000800000.pngRe-plant two existing trees; plant two new trees (all elms)

http://waterstreetweb.com/Symb075c00b700f000000000.pngReplace the cannons. April of 2009.  

http://waterstreetweb.com/Symb075c00b700f000000000.pngInstall sod; Ken Gear says that the key here is that the sod gets a lot of water. May '09.

http://waterstreetweb.com/Symb075c00b700f000000000.pngTurn on the water.

http://waterstreetweb.com/Symb075c00b700f000000000.pngAdd permanent signage regarding the history of the cannons and Cannon Square and the restoration project: date, joint effort of SVIA, the Borough and SHS.  June of 2009.

http://waterstreetweb.com/Symb075c00b700f000000000.pngCELEBRATE!!  July 4, 2009 and August 10, 2009 (195th anniversary of repressing British)

http://waterstreetweb.com/1x1.gif

Other Notes:

http://waterstreetweb.com/Symb075c00b700f000000000.pngNote that items 10-16 take place while the cannons are being restored off-site.

http://waterstreetweb.com/Symb075c00b700f000000000.pngWe have opted not to try to bring power to the square but to work on a greener, and more attractive, alternative of using solar power.

 

Project Update Following June 6 Cannon Meeting

 

1.  June 6 Meeting at SHYC.  Our project team met with Peter Fix of Texas A&M University to discuss his specialty of restoring historic cannons using an electrolytic reduction process which can take up to a year.  Apparently, it's the only known method for arresting the rusting a decay process that anything made of iron will always suffer.

 

2.  Questions.  We came away from our meeting with a few questions for Peter.

http://waterstreetweb.com/Symb075c00b700f000000000.pngWhat is your estimated budget (per cannon) for the process that you recommend?

http://waterstreetweb.com/Symb075c00b700f000000000.pngHow long would that process require for the cannons to be off site?

http://waterstreetweb.com/Symb075c00b700f000000000.pngWill your price include the waxing and painting such that the cannons are ready to be replaced directly to their carriages?

 

3.  Possible Conclusion. We are thinking that we might want to just touch up the two cannons in 2009, wait a year and then send one cannon for the electrolytic reduction process in 2010 and the other the following year. This way there would always be at least one cannon present.

 

4.  Rendering from Architect Peter Cummin. Before moving forward with our public hearing, we need to finalize our budget and we need the rendering.  Hopefully, we can schedule the hearing for sometime in July.

 

5.  Budget and Fundraising. As of today, we have $10,000 pledged from the Borough, $20,000 pledged from the state of CT, and $11,350 already collected from interested Borough citizens.  Total Project cost is estimated at $70,000, but there are still a few unknowns, particularly related to the cannons themselves.

 

Other notes of interest Posted on June 18:

 

1.  Light for Cannon Square flagpole.  From a flag etiquette standpoint, our flag should be illuminated in the evenings if it is not taken down every night.  Hence, we have decided to go with a very inexpensive solar powered light that attaches to the pole.   It is unobtrusive, very efficient and a green, earth-friendly way to go.  

 

 

 

2. Plaque for Cannon Square. After the completion of our restoration project, we are planning to install a bronze plaque that describes the history of this special place.  

 

 

Project Update as of May 19, 2008

 

1.  Historical Significance.  We will work with Stonington Historical Society to research the history of Cannon Square and, with their help, will design a prominent bronze plaque that will be permanently placed at Cannon Square upon completion of the project.

 

2.  Calendar. We have all concluded, for many reasons, that this will be a 2009 project. During 2008, we will work on:

http://waterstreetweb.com/Symb075c00b700f000000000.pngFinalizing our budget

http://waterstreetweb.com/Symb075c00b700f000000000.pngPreparation of rendering from Peter Cummin

http://waterstreetweb.com/Symb075c00b700f000000000.pngGetting approval from Warden & Burgesses

http://waterstreetweb.com/Symb075c00b700f000000000.pngEncouraging public support with public hearing.

http://waterstreetweb.com/Symb075c00b700f000000000.pngWorking on fundraising campaign

http://waterstreetweb.com/Symb075c00b700f000000000.pngDesign interim sign with rendering explaining what is happening, when and why.

 

3.  Projected Schedule:

http://waterstreetweb.com/Symb075c00b700f000000000.pngAugust 1 -- Get approval

http://waterstreetweb.com/Symb075c00b700f000000000.pngSept-March -- Fundraising with SHS

http://waterstreetweb.com/Symb075c00b700f000000000.pngNovember, 2008. Install interim sign

http://waterstreetweb.com/Symb075c00b700f000000000.pngJanuary, 2009. Remove cannons for repair.

http://waterstreetweb.com/Symb075c00b700f000000000.pngMarch, 2009. Begin landscaping and pouring of concrete slab, etc. for cannons, monument, flagpole, stone steps, water supply.

http://waterstreetweb.com/Symb075c00b700f000000000.pngMay, 2009. Re-planting of the trees, sodding the lawn.

http://waterstreetweb.com/Symb075c00b700f000000000.pngJune 1. Cannon re-installed.

http://waterstreetweb.com/Symb075c00b700f000000000.pngJuly 4. Public celebration....Back-up date is Aug. 9, the 195th anniversary of the date when these cannons were used against the British fleet.

 

4.  Our budget will include:

http://waterstreetweb.com/Symb075c00b700f000000000.pngCannon numbers from Bob Abramson

http://waterstreetweb.com/Symb075c00b700f000000000.pngProjected annual maintenance numbers, including water usage, from Bob Abramson.

http://waterstreetweb.com/Symb075c00b700f000000000.pngLandscape numbers from Ken Geer

http://waterstreetweb.com/Symb075c00b700f000000000.pngUnderground sprinkler system from Shoreline.

http://waterstreetweb.com/Symb075c00b700f000000000.pngPlanting numbers from Jim Wightman

http://waterstreetweb.com/Symb075c00b700f000000000.pngFlagpole lighting from Don Maranell

http://waterstreetweb.com/Symb075c00b700f000000000.pngTemporary sign from Jim Hicks

http://waterstreetweb.com/Symb075c00b700f000000000.pngPermanent plaque from Jim Hicks

http://waterstreetweb.com/Symb075c00b700f000000000.pngTotal current estimate for our budget is $70,000.

 

5.  Budget Summary:

http://waterstreetweb.com/Symb075c00b700f000000000.pngTotal Restoration Project budget is currently estimated at $70,000.

http://waterstreetweb.com/Symb075c00b700f000000000.pngThe cannons alone will account for almost half of that number.

http://waterstreetweb.com/Symb075c00b700f000000000.pngThe Borough has agreed to contribute $10,000 of taxpayer dollars.

http://waterstreetweb.com/Symb075c00b700f000000000.pngThe State of CT, with the assistance of Senator Andy Maynard, has pledged to contribute $20,000 for the project.

http://waterstreetweb.com/Symb075c00b700f000000000.pngThe remaining $40,000 will be raised via private fundraising efforts.

 

6.  Project Management. Jim Hicks (SVIA) will continue to coordinate with the Historical Society and Sarah Blair will continue to coordinate with architect Peter Cummin.

 

***********************************************************************