BOROUGH OF STONINGTON

Infrastructure Modernization

Master Plan

February 2005

PREPARED FOR:

The Borough of Stonington

Borough Hall, 26 Church St.

Stonington, CT 06378

PREPARED BY:

Pare Engineering Corporation

8 Blackstone Valley Place

Lincoln, RI 02865

SECTION

Section I:

Section II:

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

DESCRIPTION

Executive Summary

Existing Utility Considerations

A. Utility Location and Condition

B. Public Right of Way

C. Street Lighting

D. Zoning

Underground Utility Issues

A. Benefits

Aesthetics

Service

Emergency Response

Safety and Community Health

B. Considerations and Concerns

C. Options to Undergrounding

D. Potential Funding Sources

Federal Transportation Funding

State Funding Sources

State Statutes

TABLE OF CONTENTS

Aerial Utilities: Electric, Telephone, Cable

Underground: Storm Drains, Sanitary Sewer, Water, Gas

Federal Emergency Management Administration

PAGE

1

5

5

5

5

7

7

8

9

9

9

10

10

11

11

13

14

14

15

16

16

17 Local Funding Sources

-i- SECTION

Section III:

Section IV:

Sources

List of Exhibits:

Exhibit 1: Decorative Street Lighting

Exhibit 2: Typical Roadway Section

List of Figures:

Figure 1: Upper Borough

Figure 2: South of Cannons

Figure 3: North of Cannons

Figure 4: Upper East Side

Figure 5: Water Street

Figure 6: Wadawanuck Square

Pare Engineering Corporation

February 28, 2005

DESCRIPTION

Master Plan

A. Utility Coordination

Street Lighting

B. Property Owner Considerations

C. Construction Methodology

D. Construction Phasing

E. Project Costs

F. Permitting

Federal

State

G. Zoning Revisions

H. Action Items by Borough

Public Participation

A. October 2, 2004 Public Meeting

B. January 29, 2005 Public Meeting

-ii-

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

PAGE

19

19

20

22

23

26

34

36

36

37

38

38

41

41

45 Appendix

A.

B.

C.

D.

E.

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Correspondence:

Borough Fire Chief, September 23, 2002

Yankee Gas Services Co., December 20, 2004

FEMA Flood Insurance Rate Map

General Laws of Massachusetts Chapter 166: Section 22E: Cooperative Agreements

to remove overhead wires

Underground District Index Sheet

Preliminary Opinion of Probable Costs

Roadway Reconstruction Costs

Undergrounding Infrastructure and Utility Costs

Utility Engineering and Construction Costs

-iii- Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

EXECUTIVE SUMMARY

The Borough of Stonington (Borough) has recognized an opportunity to improve the public safety and

quality of life of its residents through the modernization of its utility infrastructure. To initiate the

improvement process, the Borough has hired Pare Engineering Corporation (PARE) to develop this

Master Plan. The Master Plan provides the Warden and Burgesses of the Borough with a tool to prioritize

reconstruction of Borough streets and sidewalks with the potential to relocate aerial utilities to

underground. The goal of this plan is to enhance the public safety of the community, improve views of

and from local homes and businesses, and increase the reliability of electrical and communications utility

services during hurricanes and other storms.

The Borough is a densely developed, historic, and increasingly affluent community, situated along the

southern coastline of Connecticut. Its location on a peninsula in Long Island Sound subjects it to

significant risks of flooding, storm surge, and high winds during hurricanes and other major coastal

storms. Aged aerial wiring and poles also increases the risk of fires. Electric, telephone, and cable utility

service disruptions have caused inconvenience, safety hazards, and potential medical emergencies for

local residents and businesses. Emergency equipment response may be constrained by low hanging

wires, downed live wires and pole fires. Undergrounding aerial utilities will significantly mitigate this

hazard. Data collected from other communities with underground power and communications links

indicate that outages are less frequent. When outages do occur, however, they may be of longer duration.

Positive vocal support from community groups prompted the Borough to investigate undergrounding of

utilities in conjunction with future reconstruction of its 5.5 miles of public rights of way (streets and

sidewalks). This public support has resulted in the requirement that developers of the former Monsanto

facility provide underground utilities within their residential and office complex.

This Master Plan includes the following information:

·  Existing Utilities and Underground Considerations

·  Underground Utility Issues

Pare Engineering Corporation

- 1 - February 28, 2005 Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

·  Master Plan

Public Participation

Preliminary Opinion of Probable Cost

Roadway Reconstruction and Underground Utility, Borough of Stonington CT

Total

Cost

Undergrounding

Cost

Roadway

Reconstruction Cost

$6,385,000

$4,560,000

$3,421,000

$5,701,000

$4,674,000

$5,112,000

$3,651,000

$2,739,000

$4,565,000

$3,742,000

$1,273,000

$909,000

$682,000

$1,136,000

$932,000

$8,437,000 $6,755,000 $1,682,000

$33,200,000 $26,600,000 $6,600,000

· 

Master Plan recommendations are based on extensive field investigation conducted in July and August

2004, coordination with utilities, research with other municipalities and their consultants, contacts with

state funding and permitting agencies, review of the literature regarding underground utility issues, and

public feedback from workshops held in October 2004 and January 2005.

The cost of relocating aerial utilities to underground can be significant. However, if construction of new

utility conduits is combined with street and sidewalk reconstruction or streetscape projects, there is value

added to the overall project. Costs for undergrounding of utilities may be in the vicinity of $4.8 million

per mile, exclusive of road and sidewalk reconstruction. Building density and specific site conditions at

various locations throughout the Borough will impact costs in each phase of construction. Cost

projections can be further refined at the completion of preliminary design. The table below presents a

breakdown for phased implementation in six districts: Upper Borough, South of Cannons, North of

Cannons, Upper East Side, Water Street, and Wadawanuck Square.

District

Location

Upper Borough

South of Cannons

North of Cannons

Upper East Side

Water Street

Wadawanuck Square

TOTAL

The Opinion of Probable Cost summarized above represents a “conservative” approach. It is

comprehensive in that it includes undergrounding of utilities for every street in the Borough, complete

road and sidewalk reconstruction, high-end Borough-owned decorative street lighting throughout,

individual service installations/connections for all customers, engineering, permitting costs and

Pare Engineering Corporation

- 2 - February 28, 2005 construction contingency. The estimate is considered reasonably safe in that it has a low probability of

being exceeded, barring inflation or new circumstances.

An “optimistic” approach may be considered whereby 7700 combined linear feet of Main Street, Water

Street and lower Elm Street is repaired instead of reconstructed (reflecting recent reconstruction); low

cost Connecticut Light & Power (CL&P) street lights are utilized; and a reduced telephone installation

cost and a lower construction contingency are applied. This would result in the following approximate

breakdown:

“Optimistic” Preliminary Opinion of Probable Cost

Roadway Reconstruction and Underground Utility, Borough of Stonington CT

District

Location

Upper Borough

South of Cannons

North of Cannons

Upper East Side

Water Street

Wadawanuck Square

TOTAL

Conclusions/Recommendations

· 

· 

· 

· 

A phased approach to utility and roadway upgrades should be implemented for six districts within

the Borough. These areas have been designated based upon the current CL&P distribution

network, land use, and relative balance between the number of properties served and lane miles in

each area.

The priority for an implementation sequence is to start underground utility work in areas located

furthest from the CL&P substation on Cutler Street, north of the railroad. Utilities in the Upper

Borough, however, may be undergrounded at any time since a separate feed provides electric

service from the CL&P substation.

Undergrounding utilities and full depth roadway reconstruction in the areas designated as South

of the Cannons and North of the Cannons, at the southern end of the Borough, would improve the

current poor road and sidewalk conditions in these areas.

Potential federal funding sources include the Federal Highway Administration and the Federal

Emergency Management Administration. State funding through LoCIP may be used to provide a

local match for some of these sources.

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Total

Cost

$4,870,000

$3,390,000

$2,400,000

$4,310,000

$3,560,000

$6,270,000

Undergrounding

Cost

$3,810,000

$2,720,000

$2,040,000

$3,400,000

$2,790,000

$5,030,000

Roadway

Reconstruction Cost

$1,060,000

$670,000

$360,000

$910,000

$770,000

$1,240,000

$24,800,000 $19,790,000 $5,010,000

- 3 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

· 

· 

The Borough may be designated as a System Improvement District to raise funds through

taxation for project implementation.

It will be important at the earliest stages of project design to initiate discussions with property

owners regarding easements.

Some areas of the Borough may be found to be impractical for implementation of underground

utility relocation due to engineering and environmental constraints. Examples may include areas

with shallow ledge, wetlands, and physical space restrictions within the right of way, among

others. These areas of constraint, if any, would be determined during preliminary design.

· 

The development of a Master Plan for infrastructure modernization, including undergrounding, is the first

step towards implementing the public improvement goals of the Borough. Once the Master Plan is

approved, the Borough may proceed into procurement of funding, design, permitting, and construction.

The Borough of Stonington acknowledges the efforts of the Stonington Undergrounding Initiative Inc.

and feedback from their June 8, 2002 public meeting. The continuing interest of their members is making

the Borough a safer community.

Acknowledged also are funding sources for this study, including the Borough of Stonington, Dodson

Boatyard, Inc., and the Mohegan Tribal Nation.

Pare Engineering Corporation

- 4 - February 28, 2005 Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

SECTION I

EXISTING UTILITIES AND

UNDERGROUND CONSIDERATIONS

Pare Engineering Corporation (PARE) has conducted an inventory of existing utilities in the Borough of

Stonington. This information was obtained from utility providers including the Borough of Stonington

for information on sewer locations and depths, CL&P for electrical aerial and underground lines and

surface facilities, and Aquarion Water Company for information on water lines. This information was

supplemented with a detailed field inventory that noted the location of water gates, sewer manholes, and

existing electrical poles/streetlights. The condition of street and sidewalk pavement was noted and photos

were taken of most adjacent properties.

A. Utility Location and Condition

Aerial Utilities

Existing electric, telephone, cable television, and fire alarm systems are predominantly overhead

throughout the Borough. Connecticut Light and Power (CL&P) provides electrical service

throughout the area. An electrical sub-station exists north of the Amtrak train tracks off Cutler Street.

The primary feed from the sub-station into the southern portion of the Borough is via an overhead line

above the Amtrak train tracks along Elm Street. A main transmission line runs down High and Water

Streets feeding the side streets within the Borough south of the railroad tracks. The Upper Borough is

fed from a separate circuit from the sub-station.

SBC SNET provides telephone service throughout the area. Comcast Cablevision of Groton, Inc.

provides cable television service to the Borough. An existing municipal fire alarm system exists

throughout the Borough. It is our understanding that the majority of the fire alarm system is on

overhead wires.

Underground Utilities

Underground electric service exists in some locations within the Borough. The new fire station on

Main Street was developed with underground electric service and a pad mounted transformer. The

eastern end of Broad Street adjacent to the new fire station has also been undergrounded. Several

locations along the waterfront on the west side of the Borough have underground utilities including

the northern portion of Front Street, west of High Street, west of Northwest Street, west of Cross

Pare Engineering Corporation

- 5 - February 28, 2005 Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Street, and west of Water Street just north of Cannon Square. Many of these services extend out to

adjacent docks and piers. Several residences and businesses have undergrounded their services from

nearby utility poles.

View of scupper drain at end of

Church Street

Storm Drains

Existing storm drainage within the Borough is

primarily closed drainage systems consisting of catch

basins, manholes and piping to outfalls along the

coastal plain. At the down gradient end of some

streets on the east side of the Borough, there are

existing seawalls with openings that convey sheet

flowing runoff to the coastal feature.

Sanitary Sewer

Sanitary sewer systems were installed under the streets of the Borough in the 1970s. As-built plans

and profiles of the sanitary sewer systems were obtained by PARE from the Town of Stonington

Water Pollution Control Authority. The profiles indicate limited areas of shallow ledge within the

Borough. Shallow ledge exists along parts of the following streets: Elihue Street, South Street,

Bradley Street, Bayview Avenue, Northwest Street, Gold Street, High Street, Broad Street, Main

Street Orchard Street and Church Street. An underground sanitary sewer pump station exists on the

east end of Diving Street.

Water

Aquarion Water Company of Connecticut owns, maintains and provides water to the entire Borough.

The underground water main system runs beneath most streets. Water mains were replaced on Ash

Street, Union Street, Grand Street, Gold Street, Front Street and Water Street south of Diving Street

in 2004.

Gas

No natural gas systems are present within the Borough. The closest gas main is located within a halfmile

south of the police station on Route 1 near Extrusion Avenue (approximately three miles from

the Borough via Route 1 and Route 1A). Yankee Gas Services Co., a division of Northeast Utilities

System, has indicated that there are no immediate plans to enter the Borough of Stonington.

However, they are always looking for the opportunity to expand their service territory (see Appendix

- 6 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

A, December 20, 2004 correspondence). Coordination with Yankee Gas should be maintained during

the design of any utility underground project to determine if there are any opportunities for combined

installation.

B. Public Right of Way

The bituminous roadway pavement within the streets of the Borough are in generally fair to poor

condition. Numerous streets, particularly in the south end of the Borough, have had water system

upgrades and have trench pavement patches throughout. Replacement of Aquarion water mains and

utility work at the former Monsanto plant has deteriorated street conditions. The public rights of way

within the streets of the Borough range from approximately 22 to 51 feet wide. Throughout most

streets, the right of way limit is at or just beyond the back edge of the sidewalk.

Church Street pole-mounted “cobra”

streetlight. Note poor pavement condition

Note slate sidewalk at 141 Water Street

The existing roadside curbing and sidewalks are generally in fair to poor condition. In front of some

properties various curb types such as granite, concrete, slate, etc. exist in a short section of roadway.

In southern sections of the Borough and in commercial areas sidewalks generally abut the curb. In

other areas a grass strip may provide a limited setback between the curb and the sidewalk.

C. Street Lighting

Street lighting throughout the Borough is predominantly from utility pole mounted lighting. Older

(several decades old) utility pole mounted lighting exists mainly in the southern section of the

Borough.

Pare Engineering Corporation

- 7 - February 28, 2005 D. Zoning

Article 9.6.3 Walkways indicates: Walkways along public streets are required and should be

constructed of slate, brick or concrete and at a minimum width of five feet.

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

- 8 - The Stonington Utility Master Plan has been proposed to improve electrical service, safety, and aesthetics

in the Borough. The following discussion outlines key benefits and issues, or challenges associated with

undergrounding utilities, and outlines potential funding sources.

A. Benefits

SECTION II

UNDERGROUND UTILITY ISSUES

Benefits frequently cited in communities where utilities are

relocated underground are aesthetics, reduced maintenance,

safety, improved utility service, and increased potential for

economic development.

crosswalks.

Aesthetics

Aesthetics are especially important in a densely developed

coastal community such as the Borough of Stonington where

homes of distinctive character have been constructed over a period of time on small lots located close

to the street. Frequently, utility lines and poles dominate both the view of the home and the view

from upper story rooms. The clutter of various wires, transformers, wooden poles and cobra-headed

streetlights diminishes scenic waterfront vistas and streetscape views. Poor pole condition, pole

location, and sidewalk disturbance caused by pole replacement also adversely affect aesthetics and

compliance with the Americans with Disabilities Act (ADA). By burying the electrical, telephone

and cable wires beneath ground, both on the street and for the connection from the street to each

building, this clutter is removed and late 1800s views are restored, before utility wires and poles

dominated the streetscape in the 1900s.

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Pole location at 149 Water

Street limits ADA-accessibility at

Removal of aerial utility wires improves the aesthetics of the Borough.

- 9 - Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Undergrounding utilities presents additional opportunities to preserve and improve the aesthetics of

the Borough, including the distinctive features of buildings, structures and places significant in local

history. To avoid conflict with sewer and water lines in the street, many of the cables may be

installed beneath sidewalks. Abutters may wish to take this opportunity to upgrade sidewalks from

asphalt to concrete, brick, or slate. Installation of underground utilities also represents an opportunity

for the Borough to reconstruct streets or to upgrade existing underground utilities such as storm

drains, sewer and water lines.

Many trees lining the Borough streets have not been allowed to achieve their natural form due to the

routine tree pruning required to assure that branches do not conflict with aerial wires. This pruning

may create poorly shaped and distorted trees with shortened life expectancies.

Service

By undergrounding utilities, residents of the Borough may be assured of more reliable electrical

service, especially during hurricanes, ice storms, and inclement weather when the likelihood of

service outages from car accidents and downed wires increases. Service has been disrupted in recent

years from conditions associated with aging aerial infrastructure including electrical equipment fires

and fires on poles. The risk of house fires from unattended candles is also a serious concern in the

Borough. The power failure on

Thanksgiving evening, 2004 reinforced the

importance of maintaining a safe and

reliable electrical service. Many residents

have installed backup generators to assure

continued service. Fuel for generators must

be carefully stored to assure the safety of

residents.

Downed wires during the July 2003 Monsanto fire

hampered emergency response.

Emergency Response

Burying wires/cables reduces the risk of

electrocution from power lines downed by

storms or accidents. Live downed wires would hinder emergency response. This was a critical factor

in controlling the fire at the Monsanto plant on July 3, 2003. Low level aerial lines may hinder the

ability of fire fighting equipment to access buildings and fight fires efficiently. The density of

- 10 - B. Considerations and Concerns

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

residences and businesses in the Borough make it vulnerable to the spreading of fire. Fast, efficient

response by the fire department is critical.

The fire chief of the Borough of Stonington indicated his support for undergrounding or burying all

power, telephone, cable and fire alarm wires as promptly as can be accomplished in his September 23,

2002 correspondence (see Appendix A):

“As chief of the Borough of Stonington Fire Department I should like to stress the

importance of safety to the fire fighters and residents and commercial property owners in

this community. With buildings so close together or even touching each other, the hazards

of overhead power lines are significantly increased and the very narrow streets, often

limiting passage of vehicles in only one direction, increase these hazards even more. The

usefulness of our fifty foot ladder trucks for reach as well as for height to access roofs and

chimneys is severely impaired by the overhead power lines.”

Safety and Community Health

Power surges in above-ground electrical lines have the potential to damage electrical equipment or

cause shorts which may cause fires in adjacent structures. By undergrounding electrical, telephone

and cable wires, this danger is minimized.

Relocation also reduces possible health risks from electromagnetic radiation. It is recognized,

however, that pad mounted electrical equipment may also have the potential to emit electromagnetic

radiation.

Undergrounding utilities is not without challenges. The most apparent challenge is cost. See Section

III.D for more details on projected costs in the Borough. Information on potential funding sources is

presented in Section II.D.

Although wires, poles and pole-mounted transformers will be removed through undergrounding,

access for maintenance of relocated facilities must be assured. These facilities will be located on both

public and private property. Manholes or handholes will be located above the underground utilities,

for access within streets. Although it is preferable to locate pad-mounted transformers on public

property, due to narrow public rights of way along many of the Borough streets, it is likely that some

of this equipment will need to be located in adjacent private yards. One pad-mounted unit serves

approximately four to eight residential buildings. Access by the CP&L must be assured through an

- 11 - Pare Engineering Corporation

February 28, 2005

easement. A 10-foot by 10-foot area is required for a typical residential pad-mounted unit. Fencing

and landscaping must not block access to these units, and units may not be painted.

In neighborhoods with small and intensively

landscaped lots, the location of pad mounted units

may be a challenge. The difficulty of siting of

these units on private property should not be

underestimated. Although most properties may

increase in value with underground utilities, it is

likely that properties with these units on site may

not appreciate at the same rate. The impact of

burying wires beneath ornamental iron fencing and

granite walls, and through flowerbeds and other

landscaping must be considered through the design

process.

Currently, street lighting is mounted on utility poles in the Borough. The style of lighting varies but it

is important to note that the lights themselves are mounted near the top of the pole and that the cone

of light extends up to 100 feet. With removal of the wooden utility poles, separate streetlights must

be installed. Luminaries on individual streetlights are typically lower, with a smaller area of

influence beneath. As such, more lights are required per street. In accordance with current Borough

zoning regulations, light sources should be shielded to prevent glare (Section 9.6). Downward casting

fixtures should be considered to prevent light pollution.

According to a 2004 Edison Electrical Institute report, underground utilities cost four times more to

maintain in urban areas than overhead lines. Underground lines require special equipment and crews

to locate the source of an outage and dig it up. Water and moisture infiltration during rainy periods

also has caused significant failures. Underground wires have more complex switch and control

needs. Buried transformers need to have air circulation, making them vulnerable to rusting and

potentially cutting their service lives in half.

The duration of an outage with underground utilities may be longer than for an outage with

aboveground service. The North Carolina Utilities Commission has documented that between 1998

and 2002 the average time to restore service with above ground utilities was 1½ hours while

- 12 -

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Pad mounted transformer located at end of

Front Street

C. Options to Undergrounding

· 

Although CL&P does not anticipate that flooding would adversely affect electrical service, it is

important to realize that routine exposure of conduits and underground facilities to salt water could

reduce the effective life of any installation.

The visual impact of aerial utilities and wooden poles may be reduced through several options. The

cost of pole relocation would be significantly lower than undergrounding utilities but the overall

benefit would be reduced as well. Under these options some or all wires would remain above ground

and therefore service would continue to be subject to storm outages.

To reduce the visibility of poles and wires in Mystic, the Town of Groton relocated several utility

lines to the rear of properties. This was a more cost effective option than the relocation of all utilities

underground. This would not be a suitable option in many areas of the Borough. Access to the rear of

Borough properties would be especially difficult in densely developed areas. The need for easements

for routine access could also disrupt landscaping and use of very small but intensively used lots.

Extensive tree trimming or tree removal to the rear of properties would probably be required.

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

underground utilities took an average of just less than 2½ hours to repair. Although many repair

activities may be accessed via manholes and handholes, some repair may require street excavation.

Although most underground systems will function during floods, if the system does go down, it may

take longer to repair.

Detours, dust and other inconveniences will be experienced during construction. In densely built

areas, with houses close to the streets, dust and noise will pose a greater inconvenience than in other

areas of Stonington where there is a greater setback from the street to homes.

Much of the lower Borough is located below the elevation of the 100-year coastal flood (see

Appendix B). With the exception of the following three areas, all land in the lower Borough is

subject to flooding:

·  North of the cannons to Harmony Street, including upland area along Water and Main Streets

·  Upland at the east end of Church Street, extending north and west of Orchard Street

Upland in the vicinity of Wadawanuck Square

- 13 - D. Potential Funding Sources

The cost of utility undergrounding is

substantial. By utilizing available state and

federal sources the burden on local

taxpayers will be mitigated. The following

outlines currently available funding

sources, including those that have recently

completed funding rounds. It is important

to recognize that with multi-phased

implementation of undergrounding in the

Borough, new funding sources may become

available in the future.

Pare Engineering Corporation

February 28, 2005

Although relocation to the rear of properties would assure that all antiquated facilities are upgraded,

the potential for future fires in the wires would not be eliminated as this infrastructure ages.

Other towns have consolidated utilities along one side of the street to improve the overall streetscape

image. By wrapping lines together it would be possible to create the appearance of fewer cables. Use

of heavier cables and stronger poles could also reduce the number of poles required. Raising wires

above sight lines along buildings could make them less visible. Another option would be to

consolidate high voltage lines and burying only low voltage wires. Although this could be applicable

to other communities, it is not a relevant solution for the Borough. Some towns have only

undergrounded the feeder lines from the street while keeping all other above ground wires in place.

With small lots, this would neither provide an overall improvement in aesthetics nor provide

improved service during storms.

Federal Transportation Funding

Federal Highway Administration: The following outlines funding sources which have been available

in the recent past. It may be anticipated that similar funding will be available when Congress passes

the US Department of Transportation reauthorization bill (SAFE-TEA, an update of TEA-21 and

ISTEA). Funding for these programs is administered on the state level by the Connecticut

Department of Transportation and the local Metropolitan Planning Organization (Southeast

Connecticut Council of Governments).

(STEAP)

Local Funding

§  Tax Increment Financing

§  Borough System Improvement District

- 14 -

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Underground Utility Funding Sources

Federal Funding Sources

§  Federal Highway Administration (FHWA)

o Transportation and Community System

Preservation (TCSP)

o Transportation Enhancements

§  Federal Emergency Management Administration

(FEMA) - Pre-Disaster Mitigation Program

State Funding Sources

§  Local Capital Improvement Program (LoCIP)

§  Small Town Economic Assistance Program Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Transportation and Community and System Preservation: The Federal Highway Administration’s

Transportation and Community and System Preservation (TCSP) Pilot Program is a comprehensive

initiative of research and grants to investigate the relationships between transportation and

community and system preservation and private sector-based initiatives. Local governments are

eligible for discretionary grants to plan and implement strategies that improve the efficiency of the

transportation system; reduce environmental impacts of transportation; reduce the need for costly

future public infrastructure investments; ensure efficient access to jobs, services, and centers of trade;

and examine private sector development patterns and investments that support these goals. A total of

$120 million is authorized for this program in FY's 1999-2003. Groton’s Mystic streetscape project

utility improvements (including undergrounding) were funded with TCSP funding ($991,307). No

local match is required for this funding program.

Transportation Enhancements: Transportation Enhancements (TE) activities are federally funded,

community-based projects that expand travel choices and enhance the transportation experience by

improving the cultural, historic, aesthetic and environmental aspects of our transportation

infrastructure. TE projects must be one of 12 eligible activities (including “landscaping and scenic

beautification” related to lighting improvements and the protection and enhancement of scenic vistas

and relate to surface transportation improvements. Funds are administered by the CT Department of

Transportation. Use of TE funds for undergrounding utilities has been controversial in Connecticut.

Although this funding source was used by the Groton/Mystic streetscape project, utility

undergrounding was not eligible for TE funding. Groton used Connecticut Local Capital

Improvement Program (LoCIP) funding for the requisite 20 percent local match for the Mystic

streetscape project.

Federal Emergency Management Administration

A significant portion of the lower borough is located within the 100-year coastal flood zone as

designated by the Federal Emergency Management Administration (FEMA). FEMA’s Flood

Insurance Rate Map for the Borough is presented in Appendix B.

Pre-Disaster Mitigation (PDM) Program: FEMA provides Pre-Disaster Mitigation funds to assist

States and communities to reach a higher level of risk management and risk reduction through hazard

mitigation planning and the implementation of mitigation projects and activities prior to a disaster

event. Application for this funding must be made through the Connecticut Department of

Environmental Protection Inland Waters office. Utility undergrounding must be proposed in response

- 15 - Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

to state and Town of Stonington multi-hazard mitigation plans to maintain eligibility for PDM

funding (these plans have been conducted on the state and local level). Eligible mitigation projects

include “Structural and non-structural retrofitting of existing buildings and facilities (including

designs and feasibility studies when included as part of the construction project) for wildfire, seismic,

wind or flood hazards (e.g., elevation, flood proofing, storm shutters, hurricane clips).”

State Funding Sources

Local Capital Improvement Program (LoCIP): LoCIP distributes funds to municipalities for

reimbursement of eligible local capital improvement projects such as road, bridge or public building

construction activities. On March 1 of each year the State Office of Policy and Management provides

a formula based entitlement to each municipality’s available LoCIP balance. These funds can

accumulate from year to year. Utility undergrounding could be incorporated within two categories:

road construction, renovation, repair, and resurfacing; and sidewalk and pavement improvement.

Projects must be included in the Borough’s approved Capital Improvement Program. The grant can

be used toward the balance on projects receiving other assistance, but cannot be used to satisfy a local

matching requirement for any state assistance program. Further information is available at:

http://www.opm.state.ct.us/igp/grants / LOCIP.HTM.

Small Town Economic Assistance Program (STEAP): STEAP funds economic development,

community conservation and quality of life projects for localities that are ineligible to receive Urban

Action (CGS Section 4-66c) bonds. The Office of Policy and Management administers the program.

Economic development projects such as reconstructing or repairing roads, access ways, and other site

improvements would be eligible. Although this program would appear to apply to the Borough of

Stonington, with competition for funding, programs in communities where economic development

objectives are more pronounced would be favored for funding.

State Statutes

No Connecticut General Statutes have been identified which enable local communities to require

placement of utilities underground, require the removal of overhead wires, or establish a funding

mechanism.

Several Massachusetts communities including Nantucket and Brookline have been successful in

planning for and removing overhead wires and poles through Massachusetts General Laws Chapter

166, Section 22. This law enables municipalities and utilities to pass ordinances and by-laws which

- 16 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

facilitate relocation of utilities underground. The MGL 166§22A through F include the following key

provisions:

· 

· 

Enables the municipality to prohibit new installation or construction of overhead wires and

requires progressive removal of poles and overhead wires and associated overhead structures

within all or any part or parts of the municipality.

Enables the municipality to identify areas for phased implementation of undergrounding.

Establishes a funding mechanism by enabling the municipality to enter into an agreement with

utilities to which “the utility shall pay to the municipality in each calendar year for a period of

years specified in such agreement an amount which shall be not less than two per cent of such

utility’s gross revenue derived during the next preceding calendar year from its customers in said

municipality and the municipality shall expend during such term as such agreement may specify

an amount not exceeding the sums paid to it by the utility pursuant to such agreement to remove

(or cause to be removed) any poles and overhead wires and associated overhead structure of such

utility and, if needed for the continuation of such utility’s service, to replace the same (or cause

them to be replaced) with underground facilities.”

· 

Local Funding Sources

Several opportunities are available to raise capital for undergrounding utilities in the Borough.

Tax Increment Financing (TIF): Tax Increment Financing provides an opportunity to create a fund

for utility improvements in the Borough of Stonington. A portion of any increase in property value

resulting from undergrounding utilities would be dedicated to a fund which would be used to meet a

portion of project costs for implementation of subsequent project phases. TIF works best in an

undeveloped area because TIF would freeze the amount of tax money that goes to the

Borough at the base value. After the development is completed, the Borough assesses the

newly improved property and the owner has to pay his full share of taxes under the same tax

rates as everything else in its category. With already developed properties the revenue

generated would be minor. TIFs are enabled by the State of Connecticut for a variety of

proposes including brownfield redevelopment. TIFs would have the benefit of taxing those

who benefit from property improvements with undergrounding utilities while avoiding taxing

residents of the Borough as a whole.

Pare Engineering Corporation

- 17 - February 28, 2005 Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

System Improvement District: Some communities establish Special Assessment or System

Improvement Districts to collect revenue for undergrounding. Either the community or the electric

utility may raise funds. The Borough of Stonington could increase the mill on Real Estate and Land

with the revenue raised to be dedicated to a fund for utility undergrounding. In order to fund

improvements to the entire Borough, the district must encompass Borough boundaries.

Under Chapter 105, sections 7-324 to 7-329 of the General Statutes of Connecticut, voters may

establish a district for any or all of the following purposes: To extinguish fires, to light streets, to

plant and care for shade and ornamental trees, to construct and maintain roads, sidewalks, crosswalks,

drains and sewers, to appoint and employ watchmen or police officers, to acquire, construct, maintain

and regulate the use of recreational facilities, to plan, lay out, acquire, construct, reconstruct, repair,

maintain, supervise and manage a flood or erosion control system, to plan, lay out, acquire, construct,

maintain, operate and regulate the use of a community water system, to collect garbage, ashes and all

other refuse matter in any portion of such district and provide for the disposal of such matter. This

statute would enable the Borough of Stonington to establish an underground utility district within the

Borough limits which would have the power to make appropriations or to levy taxes. See

http://www.cga.ct.gov/2003/pub/Chap105.htm#Sec7-326.htm.

State Legislation Required: State legislation would be required to enable either the Borough of

Stonington or CL&P to raise funds through a surcharge on either the property tax bill or on the

electric bill see MGL 166§22, above). The Town of Brookline, Massachusetts (population 57,000)

estimates that surcharges on electric, telephone and cable bills will yield between $600,000 and $1

million per year. The Brookline Board of Selectmen estimate that the average household would pay

$36 to $70 per year (the cost would be lower for those without cable service and higher for those with

electric heat). Using the Massachusetts model, everyone in town is subject to the surcharge (there is

an exemption for low income households). Utilities would be required to provide the connection to

the building, at no additional cost to the property owner. Massachusetts enabling legislation is

presented in Appendix B.

- 18 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

A. Utility Coordination

PARE has begun initial coordination with the various utility

companies that have facilities within the streets of the Borough.

Coordination letters were sent to each of the utility companies

requesting available information on the existing utility systems

and information on any planned upgrades to the system for future

implementation.

Typical congestion of aerial wires

with “cobra” pole-mounted light

fixture. Note condition of pole.

SECTION III

MASTER PLAN

The Master Plan outlined below discusses utility coordination, street lighting, property owner

considerations, construction methodology, construction phasing, projected costs, permitting and zoning.

PARE and representatives of the Borough met with Connecticut

Light and Power (CL&P) on November 19, 2004 in Borough

Hall. CL&P does all of the engineering in-house to underground

the electric utilities and no subconsultants are used. CL&P’s

design process takes approximately six months. The

communication utilities usually follow CL&P’s lead, but must

complete their design with proper coordination with CL&P

during the design phase. Typically, a meeting with all utility companies involved is set up prior to the

start of preliminary design. After master planning is complete and the Borough has funding in place,

CL&P can be contacted to propose a not-to-exceed cost for preliminary engineering. The engineering

design is 100% reimbursable to CL&P. CL&P will issue one bill to the Borough at the end of the

design. John Doane of CL&P is the contact person for this project.

The Borough is responsible for the civil design, specifications, easements, permits and construction

cost including layout of conduits and structures in coordination with CL&P, backfill, drainage,

pavement, traffic control and construction supervision. A project coordinator may be hired by the

Borough for the civil design and to coordinate with CL&P, communication companies, landowners

and the contractors regarding various design and construction aspects of the project.

With some undergrounding projects the property owner is responsible for the cost of the service from

the street to the building. The cost for individual connections to a utility pole is approximately

Pare Engineering Corporation

- 19 - February 28, 2005 Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

$2,000.00. The cost for services from an underground system would be slightly less than $2,000.00.

There would be no rate difference to customers with underground electric. To facilitate completion

of each roadway segment as expeditiously as possible (with the goal being the removal of wires and

poles), PARE recommends that the costs for connections be included within the entire project cost

and not be borne by property owners.

Above ground pad mounted transformers will be required to service approximately 6 to 8 dwellings.

The transformers cannot be placed in underground vaults. An approximate 10-foot by 10-foot

easement is needed by CL&P around each transformer. CL&P owns the transformers and painting of

the transformer boxes is not allowed by property owners. There are restrictions for landscaping in

close proximity to the transformers for proper airflow, functioning, maintenance and accessibility

particularly to transformer box doors. Some transformers hum, therefore, attempts are made to locate

transformers away from windows and bedrooms. Transformers can be placed within a floodplain.

Infrequent short periods of flooding around transformers is not a major problem. Transformer

locations must be selected early in the design process. The Borough and CL&P must coordinate this

process.

CL&P has plans to potentially replace the electric substation off Cutler Street in 2006. A second

circuit into the Borough is desired in case one circuit experiences an outage. CL&P plans to maintain

the existing overhead crossing of the Amtrak train tracks. This undergrounding project would involve

boosting the voltage from 4.16 KV to 13.8 KV.

Street Lighting

With the undergrounding of utilities and the removal of poles, separate street lighting will be

required. CL&P offers a range of decorative street lighting (see http://www.clp.

com/clpcommon/pdfs/community /outdoor/lightchoices.pdf) choices that would reflect positively

on the residential and business sections of the Borough. A print out of this website is provided in the

following two pages.

The Connecticut Dark Sky Act requires that streetlights be downward casting with less than 2.5%

uplight. A waiver may be requested through the Connecticut Department of Transportation for semicutoff

versions (i.e., “acorn” style) on aesthetic grounds. Four of the decorative fixtures presented in

CL&P’s Light Choices TM meet this requirement and are indicated with an asterisk in Exhibit 1 on the

following page.

- 20 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

CL&P offers a range of decorative poles with cast aluminum bases and 5” diameter extruded aluminum

poles. Pole heights are 12 to 14 feet to the top of fixture. Poles are generally spaced 100 feet apart but

can be closer. Decorative lighting should be considered as an architectural element within the streetscape

and, therefore, placement can be less than 100 feet apart. All CL&P street lighting must be polemounted;

CL&P does not provide street lighting with building-mounted fixtures. Brackets for hanging

baskets or banners, if desired, may be mounted on poles.

CL&P would consider other suppliers not listed in the LightChoices TM program. Any pole and fixture

requested by the Borough must meet CL&P’s wind loading and maintenance requirements as they are

the owner of the fixture and are responsible for all maintenance, repair and replacement. Few

suppliers meet CL&P’s high specification levels.

CL&P has a price/rental program for street lighting. The Borough has the option of renting fixtures

with no upfront costs or of paying the capital costs with a lower rental fee. Capital cost per fixture is

approximately $2,000 for the fixtures meeting the Dark Sky Act requirements. With upfront payment

for fixtures, the monthly operation (including electricity) is between $10 and $16 per month,

depending on the lighting source. With no upfront costs the monthly rental and operation fee is

between $30 and $40 per month. Electric supply is directly from the pad mounted transformer and is

not metered.

In addition to existing cobra-style pole mounted fixtures, CL&P also provides a standard decorative

light fixture that meets the Dark Sky requirements. This subdivision-style streetlight has a straight

square brown fiberglass pole with a lantern top on a 14-foot pole. Capital cost for each is $250 with a

monthly operation fee of $10 to $16, depending on the light source.

B. Property Owner Considerations

It is critical that electrical utility undergrounding be conducted as a seamless contract that includes

both installation beneath streets and connections to each building. Aerial service cannot be

terminated prior to making connections to EACH electrical service. Poles and aerial wiring cannot be

removed until ALL connections have been made. To facilitate project implementation, it is

recommended that the cost to connect services from the street to and including replacement of the

electrical meter on each building be included in overall project construction costs. For cost

estimating purposes, the length of installation for each service connection should be limited to a

reasonable distance such as 35 feet to meet the requirement for most properties. This would avoid

Pare Engineering Corporation

- 22 - February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

situations where individual property owners might delay a connection but will also limit the

Borough’s responsibility for circuitous routing or for connections to buildings on large properties

where the building may be set back a significant length from the public right of way.

It is recommended that project designers work closely with the Town of Stonington Building

Inspector regarding wiring permitting issues. Current building codes require 100 amp service with

circuit breakers. It may be up to the inspector to approve or reject a connection if the integrity of a

substandard service is competent. Property owners would be responsible for upgrade of any electrical

service required on the interior of the building.

CL&P will require an easement for any trench connecting the service in the street to the building.

Residential trench easements are typically 10 to 15 feet in width but may be up to 25 feet in width

beneath a driveway. The easement is generally well defined and may include restrictions on plantings

within five feet of any utility structures (pad mounted transformers). The utility company would not

be responsible for replacing any plantings within restricted areas if the area were disturbed for

operations or maintenance procedures. Generally no structures can be built on the easement or within

five feet of the easement. It is recommended that the Borough initiate preparation of easements at the

earliest project stages to assure that this does not delay project implementation. Easements must be

recorded in the Town’s land records.

C. Construction Methodology

Relocation of underground utilities requires the participation of CL&P / communications utilities and

the Borough’s contractor. Construction of the trench, conduits, and undergrounding infrastructure

such as hand holes, manholes, pads for transformers, and replacement street lighting would be

conducted by the contractor prior to installation of the cables and transformers by the utility

companies. If full roadway reconstruction is incorporated as part of the project, removal of the

existing pavement and curb would be conducted upon completion of the undergrounding

infrastructure and utility installation. Temporary pavement and sidewalk repairs will be made until

all lines are installed underground and utility poles are removed. Replacement of the gravel subbase,

curbing, pavement, and sidewalk treatment would complete the roadway reconstruction project within

the public right of way. If the roadway and sidewalk are not reconstructed, roadways should be

temporarily patched or repaved, and sidewalks restored to the original (or better) condition.

Pare Engineering Corporation

- 23 - February 28, 2005

Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

To minimize construction disruption during the popular peak summer months, many construction

activities may be conducted during the spring, fall, and parts of the winter. Trenching and paving

should be avoided during the winter, but service connection infrastructure and street light installation

may be conducted. Streets will be closed on a block by block basis to allow for trenching and conduit

installation. Traffic and pedestrian detours will be required during construction.

The Borough (and its contractor) is responsible for the installation of underground utility

infrastructure including excavation, backfill conduits, manholes and handholes and in some locations,

encasement of conduits in concrete. All infrastructure must be installed per CL&P specifications.

Communication utilities conduits (including telephone, cable, and fire alarm) will be installed side by

side with the electric conduits in a cable bank so that each utility may have access without affecting

the other utilities. Exhibit 2 presents a typical roadway section with installation of utilities

underground. The main conduit trench would be located under the roadway on a street-by-street basis,

with alignment based on avoidance of existing utility locations. Worker safety must be assured when

water or sewer trenches are located either parallel to or crossing electrical lines. PVC conduit for

primary distribution lines must have a minimum cover of 30 inches and must be encased in concrete.

PVC conduit for secondary or service lines requires a minimum cover of 24 inches and does not need

to be encased in concrete. Shallow (less than an approximate 4-foot depth) ledge encountered during

the installation of the infrastructure will need to be removed and disposed by mechanical methods.

New underground conduits will be installed in trenches in virtually all streets in the Borough.

Trenches will typically be excavated by use of a trench box which braces the sides of the excavation

and allows for a narrower trench to be dug than would otherwise be needed. The trench box is pulled

along as excavation proceeds in front of it, and backfilling takes place behind it. Open cuts with side

slopes may be necessary in some locations where a trench box is not practical.

Where groundwater is high, excavations may need to be dewatered. This is typically done by

utilizing stone material in the bottom of the excavation to create a sump from which to pump out the

water. Pumped water will be silty and will probably require a silt trap on the surface to prevent

sediment from entering waterways. Refer to Section F., Permits, for additional information regarding

discharge and treatment of water from excavations.

Typically service connections run along the property side of the sidewalk, to the hand hole and then

through the yard to the meter. By running the line to the rear of the sidewalk, future settling, if any,

should not create a trip hazard. Hand holes are required for each service connection. Hand holes are

- 24 - R. O. W. WIDTH VARIES

LIGHT POLE

SIDEWALK ROADWAY WIDTH VARIES

WIDTH VARIES

(TYP.) S

B

C

30" MIN.

F

WATER 4'-6"

COVER VARIES

(TYP. MIN. COVER)

VARIABLE DEPTH

VARIABLE DEPTH

S T B B T C

4"

SAND

6"

TYP.

12"

TYP.

GRANULAR FILL

4" PVC

CONDUIT TYP.

5' TO 6' ±

PROP. UNDERGROUND UTILITY CONDUITS

18"

MIN. IN ALL

DIRECTIONS FOR

ALL OTHER UTILITIES

SEWER DRAINAGE

G:\04159.00 Stonington Utilities Undergrounding\Dwgs\Typical Section_Overall Site .dwg, 1/26/2005 2:32:07 PM

NOT TO SCALE

Infrastructure Modernization Master Plan

approximately 1-foot by 2-foot and may be painted the color of the sidewalk. Service connections

may be bored under granite walls and ornamental fences, if necessary. This is not a problem for well

graded sandy soil, but may be more costly or problematic for other soil conditions in sections of the

Borough where ledge and outcrop are present.

Connections from the public right of way to buildings will be installed within easements on private

property. The installation is below underground sprinkler systems. Conduit trench routes through

private property must be selected to avoid mature landscaping, major tree roots, and other physical

features. Preferable locations would be beneath lawns. Construction specifications would require

that the property be restored to existing (or better) condition by reseeding lawns.

Most electric meters will require replacement unless the building’s service was recently

undergrounded. Individual electric meters must be located outside of the building in a meter box.

CL&P does not currently allow inside or basement electric meters. CL&P’s service book specifies

service requirements. A CL&P technician informs the building owner where to place the electric

meter, bring in service, and grounding requirements. All individual houses and buildings on a street

must be connected before the utility poles can be removed.

D. Construction Phasing

Six distinct undergrounding districts or areas have been identified within the Borough to provide a

logical framework for phased implementation of undergrounding projects. Area boundaries have

been established based on the following:

· 

· 

· 

A Borough map with districts identified is presented in Appendix D. Table 1 identifies project areas

and boundaries, number of parcels served within each area, the combined length of streets, and

zoning. Figures 1 through 6 identify the areas to be served within each district.

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

Existing electrical infrastructure (including substations, transformers, etc.)

Comparable service areas. To maintain equity in installation, districts have been identified to

generally serve a comparable number of parcels and street lengths.

Neighborhoods. Wadawanuck Square and the library have been included in one district to

facilitate implementation of potential streetscape projects. It is not recommended to

underground utilities along a single lengthy street since risers to poles would be required at

each intersecting street.

- 26 - Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

R

RR Rural Residence District

Table 1

Phasing Districts

District Location

Upper Borough - North of RR

South of Cannons - Ash Street and south

North of Cannons - Union and south, north

of Ash

Upper East Side - South of High and Elm,

Main and east, north of Union

Water Street - South of High, west of Main,

north of Union

Wadawanuck Square - Southwest of RR,

Elm and north, High and north

TOTAL

* Zoning Categories (bold denotes primary zone)

R-1 Residential District 1

R-2 Residential District 2

RP Residence Preservation District

Residence District

As indicated above, the main electrical feed for the Borough is located north of the rail line at the

CL&P substation, near Cutler Street. For cost efficient phasing, areas furthest north and south of the

tracks should be undergrounded as a first priority. Undergrounding in the Upper Borough may be

conducted independently of undergrounding efforts to the south. Based on its closer location to

existing Yankeegas service, it may be logical for the gas company to extend service to the Upper

Borough concurrently with undergrounding utility service.

South of the rail line phased implementation of undergrounding should start at the south end of the

system and work north toward the line crossing over of the Amtrak train tracks from the CL&P

substation. Phases would also begin at the outer branches of the electrical circuit and work toward

the main primary feeds along Elm Street, High Street and Water Street. It is recommended to

underground utilities in the most densely developed section of Water Street and vicinity in one phase.

Number of

Parcels

Combined Length of

Streets

(Approximate)

106

109

64

89

89

102

559

PW Planned Waterfront District

PC Planned Commercial District

Planned Industrial District LI

RL Reserved Land

PAD Planned Area Development

Borough of Stonington, Connecticut

Zoning *

R, PI 5,600 linear feet

4,000 linear feet PAD, R-2, R-1,

RL

RP, RL, R-2 3,000 linear feet

RP, RL 5,000 linear feet

4,100 linear feet PC, RP, RL,

PW

RP, RL, PI 7,400 linear feet

PW

29,100 linear feet

- 27 - FIGURE 1

UPPER BOROUGH PARE

8

ENGINEERING CORPORATION

BLACKSTONE VALLEY PLACE

RI 02865 LINCOLN,

401 - 334 - 4100 UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

SCALE: 1'' = 500'

FIGURE 2

SOUTH OF CANNONS PARE ENGINEERING CORPORATION

8 BLACKSTONE VALLEY PLACE

LINCOLN, RI 02865

401 - 334 - 4100 UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

SCALE: 1'' = 250'

FIGURE 3

NORTH OF CANNONS PARE

8

ENGINEERING CORPORATION

BLACKSTONE VALLEY PLACE

RI 02865 LINCOLN,

401 - 334 - 4100 UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

SCALE: 1'' = 250'

FIGURE 4

UPPER EAST SIDE PARE

8

ENGINEERING CORPORATION

BLACKSTONE VALLEY PLACE

RI 02865 LINCOLN,

401 - 334 - 4100 UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

SCALE: 1'' = 250'

PARE

8

ENGINEERING CORPORATION

BLACKSTONE VALLEY PLACE

RI 02865 LINCOLN,

401 - 334 - 4100

FIGURE 5

WATER STREET

UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

SCALE: 1'' = 250'

FIGURE 6

WADAWANUCK SQUARE PARE

8

ENGINEERING CORPORATION

BLACKSTONE VALLEY PLACE

RI 02865 LINCOLN,

401 - 334 - 4100

UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

SCALE: 1'' = 350'

Infrastructure Modernization Master Plan

E. Project Costs

Preliminary opinions of probable costs have been developed for roadway reconstruction and for

relocation of electrical, telephone, cable and fire alarm cables underground. These cost opinions are

considered conservative in that they include undergrounding of utilities for every street in the

Borough, complete road and sidewalk reconstruction for every street, high cost street lighting at 75

foot spacing on both sides of every street, all individual service installations/connections, and a

contingency factor as described below. This estimate is considered reasonably safe in that it has a

low probability of being exceeded, barring inflation or new circumstances.

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

By starting at the most southern point of the Borough and working northward a consistent and logical

progression of underground service would be implemented. CL&P recommends phasing entire

neighborhood blocks at a time. CL&P does not recommend planning to underground single lengthy

streets. This would eliminate the need to retain underground risers on poles at locations where service

converts from aerial to underground. CL&P has indicated that it will retain the power lines crossing

above the rail line from the substation north of the tracks to the Lower Borough.

Some areas of the Borough may be precluded from implementation of underground utility relocation

due to engineering and environmental constraints. Examples may include areas with ledge, wetlands

and physical space restrictions within the right of way, among others. Areas of constraint, if any,

would be determined during preliminary design.

Roadway reconstruction includes removal and replacement of the existing roadway and sidewalk.

Costs include removal of roadway pavement, adjustments in manholes, hydrants, catch basins, and

replacement of water gates, curb stop boxes, as necessary. Granite, bluestone, or other special curb

material will be removed and stockpiled for replacement (if of suitable condition). Concrete curb will

be installed in other areas. Cement concrete sidewalks will replace substandard sidewalks. Special

considerations must be taken to determine if brick or stone sidewalks must be replaced. For

construction estimate purposes, sidewalks are replaced with cement concrete, in accordance with the

zoning ordinance. Gravel borrow subbase and bituminous pavement will be constructed for the

roadway surface. The preliminary opinion of probable costs for roadway construction, including an

estimated additional 30 percent for engineering, permitting and construction contingencies, is

approximately $233 per linear foot or $1.2 million per mile.

- 34 - Infrastructure Modernization Master Plan

District

Location

Upper

Borough

South of

Cannons

North of

Cannons

Upper East

Side

Water Street

Wadawanuck

Square

TOTAL

Notes:

Pare Engineering Corporation

February 28, 2005

Costs for placing aerial utilities underground include civil work, electrical work, cable and

communication work, street lighting, and individual service connections. Preliminary opinions of

probable costs for conduit, handholes, street lights, service pedestals for street lights, and service to

buildings, including an additional 30 percent for engineering, permitting and construction

contingencies, is approximately $463 per linear foot. Preliminary opinions of probable cost for the

relocation work by CL&P, SBC SNET, and Comcast, including removal of poles and old

infrastructure, and a 20 percent contingency, is approximately $450 per linear foot.

Table 2 presents a preliminary opinion of probable costs for roadway reconstruction and relocation of

aerial utilities underground. A breakdown of preliminary opinions of probable costs is presented in

Appendix E.

1. The cost to remove and dispose shallow (within approximately 4 feet of the surface) ledge will be

determined during the design phase. Contingencies are included in the above cost estimate to cover the

unknowns including the ledge removal quantity.

2. Engineering design costs are typically approximately 10% of the construction costs and are included in the

above cost estimate table.

3. These costs are based upon the 2005 value of the dollar and do not include an estimate for inflation in the

construction market.

Table 2

Preliminary Opinion of Probable Roadway Reconstruction

and Underground Utility Engineering and Construction Cost

Roadway

Roadway Length Reconstruction Infrastructure

(Approximate)

5,600 linear feet

4,000 linear feet

3,000 linear feet

5,000 linear feet

4,100 linear feet

7,400 linear feet

29,100 linear feet

Total

Undergrounding

Cost Cost

Underground Utility Costs

Utility

Company

Cost Cost

$5,112,000 $2,522,000 $2,590,000 $1,273,000

$3,651,000 $1,801,000 $1,850,000 $909,000

$2,739,000 $1,351,000 $1,388,000 $682,000

$4,565,000

$3,742,000

$2,252,000

$1,846,000

$2,313,000

$1,896,000

$1,136,000

$932,000

$6,755,000 $3,332,000 $3,423,000 $1,682,000

$26,600,000 $13,500,000 $13,100,000 $6,600,000

Borough of Stonington, Connecticut

Total Cost

$6,385,000

$4,560,000

$3,421,000

$5,701,000

$4,674,000

$8,437,000

$33,200,000

- 35 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

An “optimistic” approach may be considered whereby 7700 combined linear feet of Main Street, Water

Street and lower Elm Street is repaired instead of reconstructed (reflecting recent reconstruction); low

cost Connecticut Light & Power (CL&P) street lights are utilized; and a reduced telephone installation

cost and a lower construction contingency are applied. This would result in the following approximate

breakdown:

“Optimistic” Preliminary Opinion of Probable Cost

Roadway Reconstruction and Underground Utility, Borough of Stonington CT

District

Location

Upper Borough

South of Cannons

North of Cannons

Total

Cost

$4,870,000

$3,390,000

$2,400,000

$4,310,000

$3,560,000

$6,270,000

Undergrounding

Cost

$3,810,000

$2,720,000

$2,040,000

$3,400,000

$2,790,000

$5,030,000

Roadway

Reconstruction Cost

$1,060,000

$670,000

$360,000

$910,000

$770,000

$1,240,000

Upper East Side

Water Street

Wadawanuck Square

TOTAL $24,800,000 $19,790,000 $5,010,000

A reasonable range of costs therefore, to modernize infrastructure throughout the entire Borough is

$24,800,000 to $33,200,000; or $852.00 to $1,140.00 per linear foot on average. Per foot costs will vary

district to district.

F. Permitting

Federal and state permits would likely be required for relocating utilities underground.

Federal

National Environmental Policy Act: Federal funding sources stipulate that the requirements of the

National Environmental Policy Act (NEPA) be met. If funding is awarded through the Federal

Highway Administration or the Federal Emergency Management Administration, it is likely that a

Categorical Exclusion must be prepared. This evaluation is less rigorous than an Environmental

Assessment or Environmental Impact Statement but still addresses potential impact for a range of

NEPA categories including wetlands, floodplain, soil, and archaeological/historical issues. Because

of proposed subsurface disturbance, FHWA required that archaeological investigations and

construction monitoring be conducted for the Groton streetscape project in Mystic. That site is near

the Pequot fort where the Mashantucket/Mohegan massacre occurred in 1637. Investigation and

monitoring may add $40,000 to $60,000 to the Mystic construction cost.

Pare Engineering Corporation

- 36 - February 28, 2005

Infrastructure Modernization Master Plan

G. Zoning Revisions

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

State

Coastal and Freshwater Wetlands Permits: Jurisdictional areas of the Office of Long Island Sound

Program are limited to areas waterward of the high tide line (or one-year annual flood). It is not

anticipated that a permit would be required although this should be confirmed during the design stage.

For utilities installed under streets and sidewalks, there would likely be no wetland impacts. Some

individual services, however, may require wetland permits.

Stormwater and Dewatering Wastewaters from Construction Activities: A general permit is required

from the Connecticut Department of Environmental Protection (DEP) Water Management Bureau for

all discharges of stormwater and dewatering wastewater from construction activities that result in the

disturbance of one or more total acres of land area on a site regardless of project phasing. The

permittee shall agree to adhere to the erosion and sediment control land use regulations of the Town

of Stonington and shall adhere to the 2002 Connecticut Guidelines for Soil Erosion and Sediment

Control, DEP Bulletin #34. No registration is required for a general permit as long as it receives town

review and written approval of its erosion and sediment control measures and follows the Guidelines.

If no review is conducted by the town, the permittee must register and comply with Section 6 of this

general permit.

For construction projects with a total disturbed area (regardless of phasing) of greater than five acres,

registration must be submitted to the DEP Water Management Bureau for authorization of discharges

under the general permit. Information on this permit is found at

http://www.dep.state.ct.us/pao/download.htm#WaterGP. The DEP Water Management Bureau

should be contacted during design to assure that any required registration is conducted and that

construction practices are in accordance with state requirements.

No revisions are recommended to the zoning ordinance at this time.

If the Borough decides in the future to prioritize implementation within designated districts to the

exclusion of other areas, it may be prudent to consider designation of Utility Conversion Overlay

Districts. Zoning regulations should then be amended to require that within each Utility Conversion

Overlay District, 1) utility companies shall be required to relocate utilities underground as part of any

routinely scheduled upgrade of service, to the greatest extend practicable; and 2) private property

- 37 - Infrastructure Modernization Master Plan

H. Action Items by Borough

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

owners shall modify their property as necessary to receive utility services from underground,

relocated or redesigned distribution systems upon implementation of property improvements

exceeding 50 percent of the assessed value of the property.

The following action items have been identified for the Board of Warden and Burgesses to continue

the process of upgrading utilities in the Borough:

·  Identify district for undergrounding, street lighting, and roadway reconstruction/resurfacing.

·  Public Meetings - Maintain project momentum by keeping project before the public through

public meetings, information sessions, and website updates.

·  Obtain Funding

Utilize Probable Estimates of Construction Costs to Obtain Project Funding -

Estimates of probable costs presented, as part of this master plan must be updated to

account for inflation, market changes, and new information. Consumer Price

Indexing or other methodology for updating construction costs should be used for

construction after 2005. Estimates of probable construction costs will be refined

during later project stages.

· 

Submit Grant Applications for Available Federal and State Funding - Coordinate

with state and federal agencies and seek support of state and federal congressional

delegations.

· 

·  Establish Underground Utility District or Special Improvement District in

accordance with Connecticut General Statute Chapter 105 - This will enable the

Borough to levy a tax to raise funds for undergrounding utilities, replacing street

lighting, and reconstructing roads and sidewalks, as required.

·  Obtain Balance of Construction Funding from Local Sources - Including Borough

bonding capabilities and assessment of any betterments. Conduct public hearing and

/ or referendum as required by Borough ordinance.

- 38 - Infrastructure Modernization Master Plan

· 

· 

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

Solicit Architectural and Engineering Services for Civil Construction Related Work -

Establish project scope of services, project area, budget and schedule for design and

construction. Draft Request for Proposals (RFP) for Engineering Services for preparation of

contract documents. Make RFP available to civil and electrical design engineering firms

(advertise, distribute). Conduct pre-proposal meeting as warranted addressing scope of work

and site-specific issues. Select firm and enter into contract.

·  Coordinate with CL&P and any other utilities - to be relocated underground to assure

all are aware of the proposed project. Establish role of CL&P in the design process.

Coordinate with Town of Stonington Building and Electrical Inspector.

·  Develop Base Map - Conduct boundary survey for Row and Easements. Locate

utilities and physical features. Topographic survey required for roadway

reconstruction.

·  Initiate Coordination with Property Owners - regarding easements, location of

transformer pads, preferred route through yards, etc.

·  Initiate Permitting - required through the Connecticut Department of Environmental

Protection. Comply with National Environmental Policy Act (NEPA) requirements

for preparation of a Categorical Exclusion, Environmental Assessment, or

Environmental Impact Statement for federal funding. Conduct archaeological

investigations, as required.

Conduct Design Hearing - upon completion of 75% plans to assure that the

community is aware of the project and its positive impacts as well as potential

construction disruption.

· 

Construction

·  Review Construction Documents - prepared by consultant(s), including Form of

Agreement for construction, bid forms, design plans and specifications for all civil

and streetscape work to be administered by the Borough.

- 39 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

·  Conduct bid process, select contractor.

·  Post public notices and service announcements to advice residents and businesses of

construction schedules and locations.

·  Coordinate with Borough and Town departments.

·  Obtain the services of a design consultant or other professional engineer to

observe/monitor construction and act as the Borough’s liaison or clerk-of-the works

during the construction process.

Pare Engineering Corporation

- 40 - February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

1. Will there be underground lines to each house?

Connecticut Light and Power Specifications).

to do it this time.

SECTION IV

PUBLIC PARTICIPATION

Two public meetings were scheduled to update the public on Master Plan progress and to integrate public

comment into the planning process.

October 2, 2004 Public Meeting

The first public workshop was held at the Borough Hall, 26 Church Street, Stonington from 10:00

AM to noon on Saturday, October 2, 2004. The workshop was attended by approximately 40

residents.

Brief remarks were made by Andrew Maynard, Warden, followed by an introduction by Jeffrey

Callahan, Burgess, and presentations by Ernie Rabideau, Pam Sherrill, and Jim Hoyle from PARE.

Handouts included an agenda, scope of work, and self-addressed comment sheet. The purpose of this

first meeting was to provide an update on data collection and to receive comments and answer

questions. The work of the ad hoc citizens undergrounding committee over the past five years was

recognized in bringing this project to this point. Funding from Dodson Boatyard and Mohegan Sun

was recognized. The second public workshop was held on January 29, 2005 with presentation of a

draft master plan. Final recommendations will be presented to the Warden and Burgesses in

February.

The following summarizes comments/questions raised at the October meeting, and responses:

Response: Yes, underground lines will include conduits in the street, as presented in the typical

section graphic, and connections for electrical, telephone and cable to each home (see 2004

2. Why weren’t utilities undergrounded when sewers were installed in the 1970s? We need the will

Response: Although it would seem appropriate to put all utilizes underground at one time, an

extensive design effort is required which would be separate from the sewer installation issues.

This would have affected the schedule and budget for the sewer project.

Pare Engineering Corporation

- 41 - February 28, 2005

Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

3. The Town needs the will to do this project, and needs to know the costs. Where else has PARE

done similar work?

Response: PARE has done similar large scale utility projects in Rhode Island and eastern

Connecticut and has a sizeable staff of engineers for utility and roadway projects.

4. What will be the tax implications, the impact on property values, and is funding available?

Litchfield and Mystic have underground utilities. What are the issues there?

Response: These issues will be investigated during the master plan phase.

Warden and / or Burgess response: Nantucket has enabling legislation to levy a surcharge on the

entire island to pay for phased undergrounding as part of a twenty-year plan. To date five blocks

in the downtown area have been undergrounded. Mystic undergrounded utilities as a streetscape

project funded by a congressional earmark. Their project was not part of a comprehensive

program. Our options may include phasing in undergrounding as part of street reconstruction

projects. The master plan is the first step to begin to look for funding. This project will be up to

the taxpayers to review.

5. Does location in a floodplain affect underground installation? We were told 20 years ago that we

could not put our utilities underground.

Response: We believe features can be designed to allow installation in a flood zone. Potential

flooding wouldn’t prohibit undergrounding utilities but it may make it more expensive.

6. There was a Streets Plan twenty years ago that has never been implemented. We need a real

schedule.

Response: We will identify priority areas and recommend a sequence for implementation.

Warden and/or Burgess: Streets in the Point area are in poor condition and are scheduled for

upgrade in the next sequence of street repair projects.

7. I thought this was the detailed study required for construction. How much did this study cost?

What happens if the electrical and other utility companies say they will not participate in

undergrounding utilities?

Response: $38,000 to prepare a master plan. This study is not prepared to the level of detail for

construction. PARE contacted Mr. Arthur Marcelynas, Connecticut Department of Utility

Control, to ask if Connecticut Light and Power could refuse to participate. Mr. Marcelynas said

- 42 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

that CL&P, per its policy, will provide the customer what it wants, but the customer must pay for

it.

8. Will the master plan include costs for construction? How do we know the costs for later phases

of construction?

Response: Current costs will be included in the master plan. The rate of inflation must be

considered in projecting costs of future phases.

9. Comments about electrical service:

· 

· 

· 

· 

It is critical to continue grounding the electrical system. One benefit of the project it to

reduce the chance of salt water corrosion, including corrosion of the aluminum pipe conduit

down the side of the house (corrosion affects the neutral ground position of the wires).

Undergrounding utilities will enable the Borough to have continuous electrical service during

power outages. Generators are loud and require fuel storage (potentially dangerous). This is

a quality of life issue that should be taken into consideration in deciding to underground

utilities.

All utilities may be wireless in the future. Why spend the money now?

Until costs for alternative power sources are comparable to traditional power service, lines

will continue to be necessary.

Our power connection to the grid comes along Amtrak tracks where sailboats have been

washed up during hurricanes. Masts short out the service. This location is not within the

Borough so undergrounding utilities would not necessarily protect service.

· 

10. Is undergrounding a done deal?

Response: No, we are preparing a master plan that will present costs and schedules for

consideration by the Warden and Burgesses and discussion by the public.

11. Please talk about the appearance of the transformer boxes and how many would there be?

Response: See circulated photos from a suburban subdivision and plans in the 2004 Connecticut

Light and Power Specifications. Electrical cabinets are required every 4 or 5 homes, depending

on the load of the line, and are generally located on property lines. Separate structures are needed

for telephone service. Cabinets can be seen at the new fire station but those are larger than what

would be required along residential streets.

Pare Engineering Corporation

- 43 - February 28, 2005

Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

12. Can transformers go in underground vaults?

Response: We will investigate that for the master plan.

13. There must be some rule of thumb for order of magnitude costs. We heard $12,000 per house in

other communities.

Response: Costs are part of the master plan effort and will be available at the next public

workshop.

Warden and/or Burgess: We have heard $350 / linear foot or $10 to 15 million for 6 miles of

Borough roadway.

14. What about street lighting? With the removal of poles we will need new fixtures. The ad hoc

committee and the Planning and Zoning Commission have investigated lighting options. What

are the code requirements for street lighting?

Response: We will include the ad hoc committee / Planning and Zoning Commission’s street

lighting options in the master plan and also include information on code requirements.

Warden and/or Burgess: More street lights will be required because fixtures will be lower.

15. We have recently heard that the cost of undergrounding, including design and installation of

street lights is $1.25 million per mile. Utilities are only required to be undergrounded on 4 to 5

miles of roadway so the cost should be less than mentioned above.

16. Safety should be considered a major marketing tool for this project.

17. Will there be a provision for continued service during hurricanes and flooding?

Response: Conduits will be pitched to drain. Structures will be as water tight as possible but may

require pumping if the site floods, especially for a long duration.

18. Charlestown NC and New York City do not lose power during hurricanes where lines are

underground. Flooding is not an issue.

19. Large boulders and ledge were encountered during recent water line replacements. Do you have

information on underground conditions? How deep are the conduits? Borough maps indicate

that there is ledge on High Street, Church Street, and Front Street.

- 44 - Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

Response: We have information from the sewer profiles. Electrical conduits are generally

installed at a more shallow depth than sewers.

20. How much clearance is required between sewer or water lines and electrical conduits?

Response: (referring to an exhibit showing a typical underground trench): 18 inch vertical and

horizontal clearance is required. Electrical conduits cannot be placed directly above a sewer or

water trench since access to those lines must be maintained.

21. How far along is the project?

Response: We are finishing the first task, data collection. That task included fieldwork, putting

the information on our plans, and contacting the utilities. We are starting the second task,

researching underground utility issues.

22. Why are some streets on the plan shaded?

Response: Streets are not shaded. The number of utility lines along a narrow street causes the

effect.

Jeffrey Callahan thanked all for their attendance and indicated that the next meeting will be held after

the first of the year.

January 29, 2005 Public Meeting

The second public workshop was held at the Borough Hall, 26 Church Street, Stonington from 10:00

to 11:30 AM on Saturday, January 29, 2005. The workshop was attended by approximately 25

residents.

Brief introductions were made by Jeffrey Callahan, Burgess. Ernie Rabideau, Pam Sherrill, and Jim

Hoyle from Pare Engineering (PARE) made a PowerPoint presentation with key findings of the draft

master plan. Handouts included an agenda; draft executive summary, district summary, a packet of

district maps, and self-addressed comment sheet. The purpose of the second meeting was to provide

an update since the first meeting on October 2, to present findings of the draft master plan, and to

receive comments and answer questions prior to issuing the final report in February. Final

recommendations will be presented to the Warden and Burgesses on February 28, 2005.

- 45 - Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

The following summarizes comments/questions raised and responses:

1. Will easements be required with each property owner? Will there be any compensation for

property owners if transformers are located on private property?

Response: Easements will be required for each property. Easements are generally 10 to 15 feet in

width and may be up to 25 feet in width for an easement along a driveway. However, easements

along a driveway would be more typical for a new subdivision and not for developed property.

Warden and / or Burgess response: Compensation would have to be addressed as part of the

easement negotiation.

2. Will pad mounted transformers be required for every two houses? How will the location of

transformers be determined? Can transformers be located to the rear of properties?

Response: Transformers generally serve five to eight properties. Preferable locations would be

along the public right of way, along the sidewalk. Although transformers could be located to the

rear of properties, access would be required for utility companies. A location along the street

would probably be preferable. Transformer locations to the rear of publicly owned property such

as the fire station could be considered.

3. Homes and businesses are built immediately adjacent to the sidewalk in many sections of the

Borough. Where would the transformer be located?

Response: These are details that will have to be looked at during design. This will be a challenge.

It may be possible to use larger transformers which could service more than eight properties.

CL&P has indicated that it will not locate transformers underground as is done in many other

locations.

4. The draft executive summary indicates that the developers of Stonington Commons at the former

Monsanto plant have indicated a willingness to underground utilities if a master plan is

completed. Please note that the developers were required to provide underground utilities,

regardless of the findings of the master plan.

Response: Text will be revised to indicate this.

- 46 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

5. Why does CL&P have the dominant role in utility relocation?

Response: Both the telephone and cable companies defer to CL&P for utility relocation

underground. Public safety with respect to live power lines is the primary concern.

6. Why would sidewalks be reconstructed? Sidewalks are the responsibility of adjacent property

owners.

Response: Tree roots have heaved sidewalks and others are cracked. Borough zoning indicates

that asphalt sidewalks are not acceptable. The cost of sidewalk reconstruction was one of the

assumptions made in the cost estimate. These sidewalks would be reconstructed with concrete.

7. What are the street lighting costs? That is one of the most expensive items. Street light costs are

cheaper in California.

Response: CL&P has indicated that decorative street lighting is approximately $2,000 per unit.

Less expensive subdivision-style lighting could be provided for approximately $250 per unit.

Although as a general rule of thumb the number of street lights would increase as the unit is

lowered from the current telephone pole mounting, CL&P has indicated that street lighting is

generally installed approximately 100 feet apart and at a height of 14 to 16 feet. This

configuration could be revised during final design. Spacing of 75 feet has been used for

preliminary cost estimate purposes.

8. You have indicated that the cost is $4.8 million per mile. Can you give us a more specific cost

breakdown by linear foot?

Response: The preliminary opinion of probable costs is $233 per linear foot for roadway

reconstruction, $463 per linear foot for undergrounding infrastructure costs, and $450 per linear

foot for utility costs (CL&P and communications companies).

9. Does the cost for roadway reconstruction assume that all roads and sidewalks are reconstructed?

Response: Yes.

10. How many streetlights would be replaced?

Response: 780

Pare Engineering Corporation

- 47 - February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

11. Can you do a linear installation along Water or Main Streets?

Response: It would be less cost effective to underground utilities along a street than to

underground the adjoining neighborhood because of the existing power distribution network.

Service would be routed through conduits along poles at the transition points between

underground and aerial service.

12. How much federal funding would be available?

Response: Federal funding could be available through the Federal Highway Administration as an

earmark through the Transportation Community System Preservation (TCSP) program or through

FEMA’s Pre-Disaster Mitigation (PDM) program. The Town of Groton received a $1 million

grant through TCSP. It is important to work closely with your congressional delegation regarding

these programs. It is highly unlikely that a federal program would provide a grant for $33 million

for this project. The southern Borough might be more suitable for PDM funding while TCSP

funding might be more appropriate along commercial streets.

13. How much would property values increase with underground utilities? How would this affect

taxes? How would a transformer pad affect property values? Please provide information from

Charlestown RI referenced at the first meeting.

Response: We will investigate this for the master plan: Charlestown does not have underground

utilities. The Town of Brookline Massachusetts is currently conducting studies to continue

undergrounding utilities. According to Brookline's information, a home's value without wires

and poles is approximately 2 percent higher than comparable homes in the community. This 2%

valuation on a $500,000 dwelling would be $10,000.

14. Would utility bills increase with underground utilities?

Warden and/or Burgess: CL&P rates would not increase.

15. Sometimes we loose power for a few seconds or for several hours. Sometimes CL&P shuts down

service during a storm as a safety measure so even if there is no pole or wire down, we loose

service.

16. Is a 30 percent contingency too high or too low? Does the cost include engineering design

services?

Pare Engineering Corporation

- 48 - February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Response: 30 percent is an industry standard for projects at the planning stage. As design

advances, many of the unknown factors will be quantified. The contingency includes design and

permitting costs as well as potential cost increases.

17. Are demolition costs included in the cost estimate?

Response: Yes, removal of poles and existing lighting, and removal of asphalt and curb are

included.

18. Do transformers buzz or hum?

Response: CL&P has indicated that some transformers do hum, even when maintained. Others in

the audience reported that transformers installed on college campuses or at other residential

applications do not make a noise. No one in the audience reported hearing a pad mounted

transformer buzz.

19. Will natural gas service be available in the Borough in the future?

Response: Yankee Gas lines are approximately three miles from the Borough, near the police

Station on Route 1. Yankee Gas might be interested in extending service, especially if it can be

combined with either roadway reconstruction or underground utility service installation. The

Borough should maintain coordination with Yankee Gas as this project proceeds.

20. Are federal grants competitive?

Response: Grants are competitive. It is important to work with your congressional delegation to

demonstrate support.

21. Do telephone and cable companies have transformer boxes as well?

Response: Yes, but they are much smaller.

22. It is important to realize that undergrounding utilities will improve safety and aesthetics.

23. Warden: We recently received a voluminous grant application and CD for the 2005 FEMA PDM

program. Our FEMA emergency management plan indicates that utilities should be put

underground.

Response: PARE would recommend that the Borough submit this application for the current

funding cycle for several reasons: You have a completed FEMA plan (one of the criteria)

Pare Engineering Corporation

- 49 - February 28, 2005

Infrastructure Modernization Master Plan

Pare Engineering Corporation

February 28, 2005

Borough of Stonington, Connecticut

recommending undergrounding utilities, you will have a completed master plan to document the

interest of the Borough and the issues to be addressed, and it may take more than one grant cycle

for an award.

24. Warden: Competition for enhancement and transportation grants is very competitive through the

Council of Governments.

25. Are the costs mentioned in today’s dollar values?

Response: Yes.

26. Would it be possible to legally establish a loan program so that property owners can pay for

required improvements?

Response: Because the goal is the removal of poles, PARE recommends that there be no direct

costs to the property owners. Connection costs should be included in the cost of installation.

This may provide an incentive for easement negotiation. Groton did not require property owners

to participate financially in utility relocation or undergrounding.

27. Have Groton property values increased?

Response: This project has not yet been constructed.

28. The cost for service connections is approximately 5 percent of the project cost.

29. Warden: The Borough is limited to 2½ times the tax burden for bonding. With fire station

construction, the Borough has reached its bonding limit through 2007. At that time the Borough

could consider a $1.5 million bond for undergrounding. Borough approval will be required.

30. People who are not here today should be provided information. We will post meetings and make

the final report available on the Borough website.

Jeffrey Callahan thanked all for their attendance and indicated that the final report will be available at

the end of February. PARE will present findings to the Warden and Burgesses on February 28, 2005.

- 50 - Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

SOURCES

Aquarion Water: Judy Simpanen, August 19, 2004

Antonio P. Franco & Associates Electrical Engineers: Tony Franco, January 10, 2005

State of Connecticut

Connecticut Power & Light

Joe Carnevale, January 12, 2005

Chris Menard, August 17, 2004

Groton, Town of: Michael Murphy, Planner, November 4, 2004

Martin Associates: Jeff Martin, December 2, 2004

SBC SNET

Dave St. Martin, September 3, 2004

Mark Miner, August 17, 2004

Phil Cote, January 11, 2005

Stonington, Town of

Town of Stonington Engineering Department, January 5, 2005

Harold Storrs, Director, WPCA (Sanitary Sewer), September 1, 2004

Yankee Gas Company:

Luanne Dinihanian, December 20, 2004

VanZelm Engineering: Brian West, January 6, 2005

Edison Electric Institute, Out of Sight, Out of Mind? A study on the costs and benefits of

undergrounding overhead power lines, by Brad Johnson, Independent Energy Advisor, January 2004

Connecticut Light & Power, 2004 Specifications and Installation Guide for Underground Service to

Residential Developments

Connecticut Light & Power, Information and Requirements for Electric Supply Below 600 Volts, 2003

Edition (“Yellow Book”)

Telephone logs:

CT Office of Emergency Management: Dana Conover, Chief of Operations, November 2,

2004

CT Dept. of Economic & Community Development: Peter Simons, Asst. Dir. Of

Infrastructure & Real Estate, November 1, 2004

CT DEP Office of Long Island Sound Program: Rick Huntley, January 4, 2005

Pare Engineering Corporation

February 28, 2005 Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

APPENDIX

Pare Engineering Corporation

February 28, 2005 A. Correspondence:

Pare Engineering Corporation

February 28, 2005

Borough Fire Chief, September 23, 2002

Yankee Gas Services Co., December 20, 2004

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

B. FEMA Flood Insurance Rate Map

Pare Engineering Corporation

February 28, 2005 Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

C. Massachusetts General Laws

Chapter 166: Section 22E: Cooperative agreements to remove

overhead wires

Pare Engineering Corporation

February 28, 2005

D. Underground District Index Sheet

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

DISTRICT INDEX

UTILITY MASTER PLAN

STONINGTON, CONNECTICUT

UPPER BOROUGH

UPPER EAST SIDE

NORTH OF CANNONS

SOUTH OF CANNONS

WATER STREET

WADAWANUCK

SQUARE

Pare Engineering Corporation

February 28, 2005

Infrastructure Modernization Master Plan

Borough of Stonington, Connecticut

E. Preliminary Opinion of Probable Costs:

Roadway Reconstruction Costs

Undergrounding Infrastructure and Utility Costs

Utility Engineering and Construction Costs

Preliminary Opinion of Probable Roadway Reconstruction Costs

Borough of Stonington

ITEM QTY. UNIT

LS

710 SY

1564 SY

7 EA

24 EA

3 EA

2 EA

2 EA

6 EA

7 EA

24 EA

1220 LF

79 CY

450 TONS

679 CY

2274 SY

1

AMOUNT

$4,260

$7,820

$525

$1,800

$675

$350

$800

$5,400

$1,225

$3,600

$24,400

$17,775

$22,500

$10,185

$7,959

$5,350

$114,624

$34,387

$149,011 TOTAL

$233 1.

$1,229,342

$1.2 MILLION

Based on Sample Roadway Segment on Water Street from Wall Street to Church Street (640 LF)

Remove and Dispose Sidewalks

Remove and Dispose Flexible Pavement

Remove and Dispose Water Gate Box

Remove and Dispose Curb Stop Box

Adjust Sewer Manhole

Adjust Drainage Manhole

Adjust Hydrant

Reconstruct Catch Basin

Water Gate Box

Curb Stop Box

Concrete Curb

Cement Concrete Sidewalk

Bituminous Pavement

Gravel Borrow Subbase

Trimming and Fine Grading

Mobilization (approximately 5%)

1. Based upon full roadway and sidewalk reconstruction after utilities are placed underground. If only

repairs to the roadway are performed, an average cost of approximately $100.00 per linear foot may

apply. The "Optimistic" Preliminary Opinion of Probable Cost as presented in the Master Plan

assumes that 7700 linear feet of Main Street, Water Street and Elm Street will be repaired, not

reconstructed. It also assumes a reduced contingency rate of 25%.

Stonington, Connecticut

February 28, 2005

SUBTOTAL

30% Engineering, Permitting & Contingency

COST PER LINEAR FEET

COST PER MILE

SAY

UNIT PRICE

$6.00

$5.00

$75.00

$75.00

$225.00

$175.00

$400.00

$900.00

$175.00

$150.00

$20.00

$225.00

$50.00

$15.00

$3.50

$5,350.00

QTY.

15,000

6,700

2,600

360

780

10

540

225,200 LF

CY

CY

TONS Temporary Bituminous Pavement Patching

Heavy Duty Handhole including Frame and Cover

Street Lights

Service Pedestal for Street Lights

Services to Building

Stonington, Connecticut

February 28, 2005

SUBTOTAL

30% Engineering, Permitting & Contingency

COST PER LINEAR FEET

1. Based upon high cost decorative street lights at 75 feet on centers, both sides of the street

throughout the Borough. The "Optimistic" Preliminary Opinion of Probable Cost presented in the

Master Plan assumes that low cost CL&P lights are purchased at $250.00 each. It also assumes

a reduced contingency rate of 25%.

UNIT PRICE

$18.00

$15.00

$16.00

$50.00

$2,000.00

$5,000.00

$15,000.00

$2,000.00

UNIT

EA

EA

EA

EA

Preliminary Opinion of Probable Undergrounding Infrastructure

and Utility Construction Costs

Borough of Stonington

ITEM

3 or 4" PVC Conduit

Trench Excavation

Gravel Borrow Fill

AMOUNT

$4,053,600

$225,000

$107,200

$130,000

$720,000

$3,900,000

$150,000

$1,080,000

$10,365,800

$3,109,740

$13,475,540 TOTAL

$463 1.

1

1

1

Preliminary Opinion of Probable Utility Engineering and Construction Costs

Borough of Stonington

Stonington, Connecticut

February 28, 2005

AMOUNT UNIT PRICE ITEM UNIT QTY.

$4,940,000

$5,600,000

$380,025

$4,940,000.00

$5,600,000.00

$380,025.00

CL&P Cost ($4 million south of tracks)

SBC SNET Cost ($1 million per mile)

Comcast Cost ($ 13.50/ LF from Mystic)

LS

LS

LS

$10,920,025 SUBTOTAL

$2,184,005 20% Contingency

$13,104,030 TOTAL

$450 1. COST PER LINEAR FEET

1. The SBC SNET cost opinion of $1 million per mile was provided by SBC SNET in a telephone conference. This

is an all inclusive cost. The "Optimistic Preliminary Opinion of Probable Cost presented in the Master Plan

assumes that SBC SNET Costs will be approximately $750,000 per mile due to their following CL&P, with

construction planning in place.